Unloading and assembly of silos in Gorzow Wielkopolski

Location: Gorzow Wielkopolski
Term: June 2020
Scope of work: unloading, plumbing and placing 2 silos

Photo report from relocation

The course of work on the unloading and assembly of silos in Gorzow Wielkopolski

We started the beginning of June with the assembly of 2 storage silos at the construction site of the production hall in Gorzow Wielkopolski. Thanks to favorable weather conditions, unloading and assembly took place without any difficulties.

The silos were delivered using oversized transport. One of the challenges (due to the limited space) was to find a suitable location for the cranes so that unloading could take place in the safest possible conditions. Unloading and plumbing was done with 2 hydraulic cranes – the main class of 50 tons and the auxiliary class of 25 tons.

At the beginning, we attached the slings with a dedicated traverse. The plumbing process took place in no wind conditions so as to minimize the risk of fluctuations when moving the element. Finally, we installed a ladder and a platform connecting 2 silos. The silos were 16 meters high, so we used a dedicated articulated lift for assembly.

The entire order was completed within 2 business days.

Machines and devices used during the execution of the order

  • Basket platform.
  • 50 ton hydraulic crane.
  • 25 ton hydraulic crane.
    Slings and hooks.